CELAYA SOLUTIONS RESEARCHEL PASO DEL NORTE / DATA CENTERS

// Position · El Paso del Norte corridor

Data centers, water, and power, on terms the public can enforce.

I am not against data centers. I build the equipment they run on. My concern is narrow and factual: El Paso and Santa Teresa are approving facilities that consume large volumes of our water and power without enforceable limits, and shifting the cost and risk onto residents.

8.71MGD
Documented regional water surplus, the figure the City has never shown its math against
17.9%
Share of that surplus the Northeast El Paso facility alone is authorized to draw
2,880MW
Self-supplied gas microgrid authorized for the Santa Teresa project across the basin
50jobs
Permanent jobs required for one El Paso campus, total, not per phase
01 / Where I stand

The rules are too weak, and the same pattern will repeat unless the City sets enforceable terms now.

My background is electrical infrastructure: more than twelve years, including critical power systems at large data centers and switchgear manufacturing. I have read the public records behind the region's data-center projects and run the water and power math, and I have submitted that work, sourced and reproducible, for the Council's consideration.

The draft Data Center Policy Framework is a good list of goals. It has no teeth. It should be replaced with an enforceable ordinance: a special permit and a Council vote, a buffer from homes and schools, a potable-water cap with reclaimed-water cooling, public metering and reporting, one hundred percent applicant-paid cost causation, daily penalties, and a teardown bond.

I do not raise the specifics of any one deal to single out a company. Each project followed the rules that exist today. The point is that the rules let our water and power leave the table without limits, and the City can fix that with a law that applies equally to everyone, before the next signature.

“I am not against data centers or technology. I build the equipment they run on. My concern is that the City is approving facilities that consume large volumes of our water and power without enforceable limits.”

From the public comment letter
Christopher Celaya to Mayor Johnson and the El Paso City Council · June 9, 2026

02 / The one question I ask answered on the record
On the record

Which water-supply number did the City rely on to find we have enough water for data centers, and where is it published?

El Paso Water provides on the order of 105 million gallons per day, with a documented regional surplus on the order of 8.71 million gallons per day. The Northeast El Paso facility alone is authorized for up to 1.5 million gallons per day. If that supply number cannot be shown with a citable source, the approvals rest on trust, not data.

105
MGD provided by El Paso Water
8.71
MGD documented surplus
1.5
MGD authorized, one facility
17.9
% of surplus, that facility alone
03 / What the public record shows

What El Paso gave up for one data center.

Every line below is drawn from the executed agreements for the Northeast El Paso project (Chapter 312, Chapter 380, and the Stan Roberts records), counterparty WURLDWIDE LLC, d/b/a Statue LLC.

What the City gaveFrom the signed agreements
01
80% property-tax abatement, 10 years per phase, up to 5 phases (Chapter 312)
02
A second 80% property-tax grant, 15 years per phase, with no dollar cap (Chapter 380)
03
$5,000,000 in Texas Economic Development road funds
04
Up to $9,000,000 reimbursing the company's road costs
05
All impact, permit, review, and park fees waived
06
~1,039 acres of City land, sold to the company
07
A 35-year lock-in that auto-extends, with a promise not to tax or regulate data centers for the term
What the City gotIn return
50
permanent jobs, total. Not per phase. Remote workers count toward it. Wage floor near $16.43/hour. Jobs not required for roughly a decade.
·
A building the company is not required to construct
·
Inspection once a year, escorted, under a non-disclosure agreement
And the oversight the City surrendered
×
No cap on water. Terms sit in a separate El Paso Water agreement that is not public.
×
No cap on power. No ceiling on electrical demand anywhere in the contracts.
×
No cost-causation. Nothing makes the company pay for the utility upgrades it forces, so residents' bills absorb them.
×
No noise, air, or environmental limits, and no community-benefit requirement.
×
A duty to fight residents' public-records requests for the company, at the Texas Attorney General.
×
Almost no clawback if the project underdelivers.

El Paso cannot easily undo this deal. It can refuse to repeat it. The fix is a city law that sets clear, equal terms before the next signature.

04 / The region as a whole

Three projects. Two states. One basin and one airshed.

These facilities draw on the same regional water basin and the same air. They are being approved at the same time, with no public study of the three of them together.

Northeast El Paso, TX
Meta
WURLDWIDE LLC, d/b/a Statue LLC
Authorized potable water, full build-out1.5 MGD
Grid load~100 MW
Permanent jobs required50 total
Socorro, TX
Wiwynn
El Paso County, same basin
Grid load~150 MW
Cumulative regional studyNone on file
Shares aquifer with El PasoYes
Santa Teresa, NM · Doña Ana County
Project Jupiter
Case D-307-CV-2025-02766
Self-supplied gas microgrid2,880 MW
Nitrogen oxides emitted~499 tons/yr
Water claims backed by technical dataNo
2,173 MW

El Paso Electric reports a record peak demand of 2,173 MW against roughly 2,300 MW of capacity, projects large-load-driven needs of up to 1,650 MW, and has proposed billions in upgrades and a residential rate increase. El Paso is non-ERCOT, so the 2025 Senate Bill 6 large-load protections do not reach it. That is the regulatory gap a city ordinance can close.

05 / What I am asking the Council to do

Five things, before the next approval.

1

Adopt an enforceable ordinance

Generally applicable to all hyperscale data centers, in place of the non-binding framework: special permit and Council vote, a 1,000-foot buffer from homes and schools, a potable-water cap with reclaimed-water cooling, public metering and reporting, 100% cost causation, daily penalties, and a teardown bond.

2

Publish the water-supply number

State the supply figure relied upon for data-center approvals, with its source. If the math cannot be shown, do not approve further capacity.

3

Require a cumulative regional study

Count Meta, Wiwynn, and the adjacent Doña Ana County project together, for water and power, before any new approval, phase, or incentive.

4

Make operators pay for what they cause

One hundred percent of the utility upgrades they trigger, with no rate increases on residents, and require the water and interconnection service agreements be filed with the City and made public, redacted only as the law requires.

5

Require a decommissioning bond before operation

Financial assurance equal to the full cost of teardown and site restoration, posted before a certificate of occupancy, so an empty facility never becomes the public's liability.

06 / The work on file

What I have built and submitted.

Independent, sourced, and reproducible. Not an official City of El Paso publication, and not legal advice.

Inside the packet
Part A
Public comment letter

The position, the one question, and the five asks, addressed to the Mayor and Council.

Part B
Exhibit

What El Paso gave up for one data center, line by line, from the executed agreements.

Part C
Model ordinance

A filled, neutral, court-ready ordinance written for introduction and City Attorney review.

07 / The movements

How this got on the record.

Feb 17, 2026

Council directs staff to draft a framework

The City Council directs staff to develop a data center policy addressing impacts on water, energy, infrastructure, and the community.

Feb 2026

CSR water analysis

I run the regional water-supply math: the 105 MGD provided, the 8.71 MGD surplus, and the 17.9% one facility is authorized to draw.

Celaya Solutions water analysis
Spring 2026

Load study, instrument CS-INST-007

The El Paso Electric load study: record peak against capacity, the large-load need, the proposed upgrades and rate increase, and the non-ERCOT regulatory gap.

Citing EPE 2024 System Expansion Plan, EPE All-Source RFP (July 2025), and others
May 2026

City staff publishes the draft framework

The staff Data Center Policy Framework circulates: a list of goals, with no enforceable limits.

Jun 9, 2026

Public comment packet submitted

The letter, exhibit, and model ordinance go to the City Council and City Plan Commission, copied to the City Clerk for the record and the City Attorney.

Jun 15, 2026

CORRIDOR goes public

The full document set for all three projects opens to the public, searchable, with every answer carrying its sources.

Ongoing

Available to brief, at no cost

Open to brief the Council, the City Plan Commission, or City staff on the analysis and the ordinance.

08 / Where this is being discussed

Out in the open.

r/ElPaso and the local conversation

I have been posting this work and answering questions in public. If you want to weigh in, push back, or ask for a source, these threads are the place. The record is meant to be argued with.

09 · Engage

I will brief Council, the Commission, or staff. At no cost.

If you are a resident, a reporter, or sit on the Council, and you want the analysis walked through or the ordinance explained, reach out. The math is reproducible and the sources are open.

✓ Independent · sourced · no fee

Independent, sourced, and reproducible. Not an official City of El Paso publication, and not legal advice. Company and agency names are used only to identify the public matters discussed. Every figure on this page is drawn from the executed agreements and public filings compiled in the companion Evidence Record. Citations to area facilities support generally applicable standards and do not direct any proposed ordinance at a single project. Prepared by Christopher Celaya, Celaya Solutions Research LLC, El Paso, Texas, June 2026.

CELAYA SOLUTIONS RESEARCHEL PASO DEL NORTE / DATA CENTERS